Construction of TechCulverts® for Kanpur-Kabrai Section on NH-86 from KM 7.430 to KM 130.0 in the state of Uttar Pradesh, India.

Project Details

SIZE

TechCulvert® Size

2×2, 3×2, 4×2 and 6×2

OWNER

National Highway Authority of India (NHAI)

CONTRACTOR

PNC Infratech Ltd.

CONSTRUCTION YEAR

2014

DESIGNER + CONSULTANT

Terre Armée (Reinforced Earth India Pvt. Ltd.)

Background

This project in the Kanpur-Kabrai section of the NH-86 included installation of precast TechCulvert® at 41 water crossing locations. TechCulvert® was selected over other conventional cast-in-place concrete culvert systems to expedite construction and maintain better quality control, which otherwise becomes an issues with conventional methods.

The TechCulvert® system was adopted based on Terre Armée’s extensive background and engineering knowledge of precast structures, which resulted in a commercially viable project that provided both superior quality and reduced construction time.

Challenge

This project proved to be a breakthrough in the precast industry by providing a superior quality product and minimized time for installation. The system had to provide flexibility in terms of ease of construction without disturbing daily traffic. Terre Armée in India had to meet a construction period completion target of 7 months.

Solution

Terre Armée in India took advantage of the design customization of its shutter moulds to meet the requirements of the specifications. A single casting yard was set up at Moudha for precasting activity. To further economize the effort, a standard width of 1.75m for the TechCulvert® was accepted, which balanced the benefits of construction efficiency against the challenges posed by handling and transportation of precast units. The precast units were cast simultaneously, inclusive of side walls and slab. The raft was cast in-situ after installation of individual units at the site. This system provided the additional advantage whereby individual units are stitched on top and bottom, allowing the TechCulvert® system to behave monolithically.

The average time for site preparation and installation was 3 days from commencing of excavation to final installation.